越流侵食・浸透のメカニズムを把握するための小型堤防による越流侵食実験
與田 敏昭中川 一関口 秀雄岡 二三生後藤 仁志小俣 篤
著者情報
ジャーナル フリー

2010 年 16 巻 p. 347-352

詳細
抄録

There is not enough of the necessary scientific and technical data and method to enhance the measures against seepage of river embankment due to high water-level and against its erosion due to overtopping of river water. This experimental study was done to understand mechanisms of river embankment deformation by seepage flow and erosion due to overtopping water by using small-scaled physical model (height of embankment is one meter). Experiments were carried out under the several hydraulic and soil conditions such as overflow depth, degree of soil compaction, moisture content in the embankment, etc.

From those experiments, it was found that wet condition in the embankment significantly effects on the eroded locations, resulting shapes and sediment volume yielded that is strongly depend on the degree of soil compaction. It was, therefore, shown that operation and management of embankment, especially soil property, is very important to keep embankment safe from seepage and erosion due to overtopping.

著者関連情報
© 2010 土木学会
前の記事 次の記事
feedback
Top