2015 年 80 巻 715 号 p. 1969-1977
After Tohoku Earthquake and Tsunami 2011, with the view to compensate for the production capacity of prefabricated major manufacturers and contribute to economic rehabilitation, several builders located in affected prefectures undertook contracts to construct temporary houses. Based on detailed interviews with the 12 builders in Iwate Prefecture which supplied temporary houses, this article examines how regional builders produced temporary houses in terms of challenges and measures to deal with them. The findings offer basic knowledge concerning how regional builders could function in production activities in emergency situations.