This is the report of the Construction of the Ferro-Nickel Smelting Plant in Pomalaa, Indonesia wnzcn is me project or P.T. Aneka Tambang.
Pacific Metals Co., Ltd. took up the role of General Consultant and proceeded the Performance Guarantee Test followed by the Technical Assistant after the Commercial Operation.
This Ferro-Nickel Smelting Plant is the first Ferro-Alloy Smelting Plant in Indonesia, and is considered as the first step of industrialization of Indonesia as the national project.
In August 1970, Basic Memorandum to cooperate to this project was signed and basic agreement was signed in Sept. 1971 together with Technical Assistant Agreement.
The construction at site started from Oct. 1973, and construction was completed in Nov. 1975 just as scheduled in the original project plan. On that date electric furnace was started operation and Performance Guarantee Test was completed in April 1976.
1. The outline of the project is as follows;
(1) Smelting Process Rotary Kiln electric furnace process.
(2) Ore low grade garnilite nickel ore.
(3) Products low carbon Ferro-Nickel.
(4) Production Capacity 4, 000ton Ni+Co metal equivalent per year.
(5) Main Equipment
Ore treatment equipment screening, crushing, mixing plant.
Ore calcining plant rotary kiln 4.0
mφ×90
mSmelting furnace 20, 000kVA electric furnace 5.6
m×15
mRefining furnace oxidizing shaking converter 15t/charge desulphurizing ladle 15t/charge
Oxygen plant 300
Nm3/hour
Power plant diesel generator 5, 700kW×5
2. The characteristics of the project.
The design of the equipment is based on the 25, 000kVA plant in Hachinohe and has been modified based on the operation of 40, 000kVA plant which is the most modern Ferro-Nickel electric furnace smelting plant in Japan, and the equipment are all supplied by Japanese machineries manufacturers.
3. The result
The Performance Guarantee Test was succeeded in April 1976, and the project was completed exactly according to the schedule and design.
抄録全体を表示